Sunny Reach Int'l Corp


USED DIESEL,HFO,GAS GENERATOR,ENGINE,MARINE ENGINE PARTS,CRANKSHAFT,ALTERNATOR

POWER PLANT

  • Pages: 1
  • 150MW 13800V 50HZ THERMAL GENERATOR 2009 X 2

    POWER PLANT

    150MW 13800V 50HZ THERMAL GENERATOR 2009 X 2
  • 30MW-WARTSILA 12V46A 10860KW 500RPM GENERATOR 1996 X 3

    POWER PLANT

     30MW-WARTSILA 12V46A 10860KW 500RPM GENERATOR 1996 X 3

  • 50MW THERMAL POWER PLANT x 2

    POWER PLANT

    50MW THERMAL POWER PLANT x 2
  • DAIHATSU 6DK-36 2750KW 50HZ 6600V 2001 X 3

    POWER PLANT

    DAIHATSU 6DK-36 2750KW 50HZ 6600V 2001 X 3 average 32000 hours, run by diesel fuel,available run HFO by attached HFO treament module package sell
  • GE P9171 180MW GAS TURBINE--2014x 2

    POWER PLANT

     Chapter 2 Crew Introduction

    The units to be sold include: 2×180MW gas-steam combined cycle generating units and ancillary equipment. During operation, the entire generator set was in good condition and had stable performance. After exiting operation, all equipment of the unit has been receiving excellent and professional maintenance and is always in a standby state.

    一.The first gas -steam combined cycle generator set

    (一)The first gas -steam combined cycle generator set

    1. The #1 gas turbine generator set is produced by the French branch of the American GE Company . The model is MS-9001E (PG9171E) , turbine number: 890047 . Rotating speed: 3000RPM, rated power: 123.4MW . The gas turbine is started by an electric motor and the fuel is light diesel / heavy oil /natural gas . 

    Generator model: 1# machine: 954*010; capacity is 170MVA, voltage level 15KV, frequency 50HZ, power factor 0.8, cooling method is air cooling, three-phase two-pole; excitation method is brushless excitation. The control system is MARK-6e.

    2. The boiler is a Q1153/526-173.6(33.3)-5.9(0.67)/500(257) (no supplementary combustion, three-pressure, suspended vertical, forced circulation) waste heat boiler produced by Hangzhou Boiler Group.

    3. The steam turbine is an N60-5.6/0.56/527/255 double -pressure, single-shaft, single-cylinder, impulse, condensing steam turbine generator produced by Harbin Steam Turbine Factory Co. , Ltd.

    4. The first gas-steam combined cycle power generation unit ( #1 gas turbine, #2 boiler and #2 steam turbine ) was put into commercial operation on November 9, 2004 (burning heavy oil), and was converted to oil in January 2010. Natural gas, LNG natural gas power generation operation was completed in November 2010, and natural gas was connected to the CNOOC pipeline in July 2014. The #1 gas turbine has operated for a total of 36,770 hours (including 1,7000 hours of heavy oil operation ) , with 2,356 ignition starts and 51 interruptions.

    ( 1 ) In February 2010, the #1 machine underwent its first planned overhaul (in conjunction with the oil-to-gas conversion). The overhaul mainly replaced the turbine first-stage moving blade (new WOOD part), the first-stage nozzle and the compressor first-stage stator blade, and replaced the #2 and #3 bearings . 

     

    These two gas-fired units were stopped under normal use at the end of December 2023. The current situation is that the output power has been disconnected from the network and the gas has been disconnected. All equipment is under normal maintenance. The insulation and heating of some generators, the dehumidification and insulation of the control cabinet, and the water circulation system are all under protection.

    Costs for disassembly, packing of containers, and transportation to the port are being assessed.

     

     

    ( 2 ) In April 2015, the #1 gas turbine underwent mid-term maintenance and DLN transformation was carried out simultaneously . The first stage turbine blade and #2 bearing bush front and rear air seals were replaced.

    ( 3 ) In December 2016, gas turbine #1 underwent planned overhaul . Mainly replaced the turbine second-stage moving blade, third-stage moving blade (GE new part), first-stage nozzle, second-stage nozzle, first-stage compound ring, second-stage compound ring and compressor second-stage stator vane, and replaced #2 , #3 bearing.

    ( 4 ) In December 2018, the #1 gas turbine underwent maintenance . Mainly replaced the #2 bearing bush front and rear air seals, air intake filter element and intake filter stainless steel bracket, primary and secondary fuel nozzles, transition section, #4 bearing bush top shaft oil pipe; oil mist separator system modification, air intake filter chamber and inlet filter Gas elbow anti-corrosion, etc.

    (5) #2 steam turbine will undergo planned overhaul in 2007 and 2015.

    (6) The #1 gas turbine generator underwent planned overhauls in January 2007 (processing of corrugated sheets in the stator slot of GE) and April 2015. Generator #2 will undergo planned overhaul in April 2015 .

    ( 7 ) In January 2010, the company switched from oil to gas, and furnace #2 was overhauled. Mainly increase the heating surface of the #2 boiler condensate pipe box and remove all soot blowing systems of the boiler.

    The combined cycle equipment was officially decommissioned on July 15, 2009.

    the gas turbine generator set is as follows ( ISO working condition):

    Operation mode

    fuel

    power

    Heat rate

    efficiency

    Exhaust gas temperature

    base load

    natural gas

    123.4 MW

    10650kJ /kWh

    33.80%

    539℃

    light oil

    121.3 MW

    10730kJ / kWh​​

    33.55%

    539℃

    heavy oil

    117.2 MW

    10968 k J/ k W h

    32.82%

    525℃

     

    (2) The second gas -steam combined cycle generator set

    1. The #3 gas turbine generator set was put into operation in December 2004 and will cease operation in December 2023. The equipment is produced by the French branch of the American GE Company . The model is MS-9001E ( PG9171E), and the turbine number is 890047. Rotating speed: 3000RPM, rated power: 123.4MW . The gas turbine is started by an electric motor and the fuel is light diesel/heavy oil/natural gas.

    Generator model: 1# machine: 954*014; capacity is 170MVA, voltage level 15KV, frequency 50HZ, power factor 0.8, cooling method is air cooling, three-phase two-pole; excitation method is brushless excitation. The control system is MARK-6e.

    2. The boiler is a Q1153/526-173.6(33.3)-5.9(0.67)/500(257) (no supplementary combustion, three-pressure, suspended vertical, forced circulation) waste heat boiler produced by Hangzhou Boiler Group.

    3. The steam turbine is an N60-5.6/0.56/527/255 double -pressure, single-shaft, single-cylinder, impulse, condensing steam turbine generator produced by Harbin Steam Turbine Factory Co. , Ltd.

    4. The second set of gas-steam combined cycle generating units ( #3 gas turbine, #4 boiler and #4 steam turbine ) was put into commercial operation on December 6, 2004 (burning heavy oil), and was converted to oil in January 2010. Natural gas, LNG natural gas power generation operation was completed in November 2010, and natural gas was connected to the CNOOC pipeline in July 2014. The #3 gas turbine has operated for a total of 32,691 hours (including 16,627 hours of heavy oil operation ) , with 1,972 ignition starts and 50 interruptions. 

    1. In August 2010, #3 gas turbine underwent its first planned overhaul (cooperating with oil-to-gas conversion). Replace the first stage moving blade of the turbine, the first stage nozzle, the first stage stator vane of the compressor and the #2 bearing bush.

    2. In May 2014, the #3 gas turbine underwent mid-term maintenance. The DLN transformation work was completed simultaneously.

    3. Mid-term revision was carried out on March 3, 2016. Replace the first stage turbine blades and transition section;

    4. In December 2017, the #3 gas turbine underwent planned overhaul. Mainly replace the turbine with one jet and two jets, one return, two return, two motion and three motion.

    5. Steam turbine #4 will undergo planned overhaul in 2008 and 2014.

    6. The #3 gas turbine generator underwent planned overhaul in December 2006 (the corrugated sheet in the stator slot of GE Company was processed) and March 2014. Generator #2 will undergo planned overhaul in April 2014 .

    7. In August 2010, the company changed from oil to gas, and the #4 boiler was overhauled. The heating surface of the #4 boiler condensate pipe box was mainly increased, and all the soot blowing systems of the boiler were removed.

     

     

     

  • GE PG9171E 123MW 2011 158HOURS

    POWER PLANT

    GE PG9171E 123MW 2011 158HOURS
  • GE10 15MW 10500V GAS TURBINE POWER STATION 2005 surplus new

    POWER PLANT

    GE10 15MW 10500V GAS TURBINE POWER STATION 2005 surplus new
  • SIEMENS SST-400 30MW 10500V STEAM TURBINE SURPLUS NEW X12

    POWER PLANT

     SIEMENS SST-400 30MW 10500V STEAM TURBINE SURPLUS NEW -2017 X12

  • SURPLUS NEW 135MW COAL FIRED POWER PLANT 2016

    POWER PLANT

    SURPLUS NEW 135MW COAL FIRED POWER PLANT 2016 never used
  • WARTSILA 12V46A 10510KW 50HZ 10500V 1996X 3

    POWER PLANT

     WARTSILA 12V46A 10510KW 50HZ 10500V 1996X 3

  • WARTSILA 18V32 9706KVA 60HZ 6900V 2003 X 2 TEST HOURS

    POWER PLANT

    WARTSILA 18V32 9706KVA 60HZ 6900V 2003 X 2 TEST HOURS after installed only test hours since new. excellent condition.
  • WARTSILA 18V32 9706KVA 60HZ 6900V 2003 X 2 TEST HOURS

    POWER PLANT

    WARTSILA 18V32 9706KVA 60HZ 6900V 2003 X 2 TEST HOURS only test hours since new.
  • Pages: 1